Below is an archive of past traffic alerts and construction updates, organized by month.
July 2021
Lane Opening Graphic – July 26, 2021
Weed Removal and Median Maintenance Graphic – July 22, 2021
Nighttime Work Graphic (Roadway Striping) – July 20, 2021
Water Pipe Milestone Graphic – July 1, 2021
June 2021
On Thursday, June 24, 2021, Supervisor Katie Rice and the Upgrade the Drake team hosted an online community meeting to provide an update on construction for the rehabilitation project and on the ongoing streetlighting assessment study. Below are the presentations and recording from this meeting:
Project Update Presentation
Streetlighting Presentation
Meeting Recording
Paving Graphic (U.S. 101 Ramp Closure) – June 24, 2021
Signal Detection Social Media Update – June 23, 2021
Paving Safety Enhancements Social Media Update – June 18, 2021
Paving Operations Social Media Update – June 10, 2021
Paving Operations (Ross Terrace to Eliseo Drive) Night Work Alert – June 7, 2021
Paving Operations (Ross Terrace to Eliseo Drive) Map and Schedule – June 7, 2021
May 2021
Recycled Water Graphic – May 27, 2021
Water Pipeline Installation (Eliseo Drive to U.S. 101) Traffic Alert – May 23, 2021
Water Pipeline Installation (Eliseo Drive to U.S. 101) Map – May 23, 2021
HAWK Beacon Activation – May 17, 2021
Night Work Alert on Eliseo Drive and Del Monte – May 6, 2021
April 2021
Red Arrow Safety Infographic – April 19, 2021
Traffic Signal Switch (College, Laurel Grove, Bon Air, La Cuesta) Traffic Alert – April 5, 2021
Traffic Signal Switch (College, Laurel Grove, Bon Air, La Cuesta) Map – April 5, 2021
Ross Terrace Night Work Traffic Alert – April 5, 2021
Ross Terrace Night Work Map – April 5, 2021
March 2021
Ash Avenue Construction Graphic – March 24, 2021
Wolfe Grade Crosswalk Graphic – March 12, 2021
Traffic Signal Switch (Laurel Grove, Wolfe Grade, Bon Air) Traffic Alert – March 9, 2021
Traffic Signal Switch (Laurel Grove, Wolfe Grade, Bon Air) Map – March 9, 2021
La Cuesta Crosswalk Graphic – March 5, 2021
February 2021
La Cuesta Fountain Update – February 24, 2021
Street Light Installation – February 1, 2021
January 2021
Traffic Light Installation – January 7, 2021
December 2020
Holiday Construction Update – December 18, 2020
Eliseo Drive Crosswalk Construction Update – December 18, 2020
Eliseo Drive Crosswalk Construction Map – December 18, 2020
Laurel Grove Avenue Closure Traffic Alert – December 10, 2020
Laurel Grove Avenue Closure Map – December 10, 2020
HAWK Beacon Infographic – December 9, 2020
November 2020
Additional Construction Hours – November 16, 2020
Laurel Grove Avenue Crosswalk Closure – November 12, 2020
Manor Road Closure Traffic Alert – November 11, 2020
Manor Road Closure Map – November 11, 2020
Additional Construction Hours – November 2, 2020
October 2020
Water Main Line Graphic – October 28, 2020
Laurel Grove Avenue Sidewalk Closure – October 19, 2020
Construction Activities – October 19, 2020
Construction Activities – October 12, 2020
Construction Activities – October 5, 2020
September 2020
Construction Activities – September 28, 2020
Construction Activities – September 21, 2020
Construction Activities – September 14, 2020
August 2020
Construction Activities – August 26, 2020
Construction Activities – August 12, 2020
Broken Pipeline Graphic – August 5, 2020
Construction Hours Update – August 3, 2020
July 2020
Rosy Path Closure – July 29, 2020
Construction Hours Graphic – July 7, 2020
Additional Construction Work Graphic – July 6, 2020
June 2020
Virtual Open House Graphic – June 3, 2020
Project Update Newsletters
April 2021
April 2021 Project Update Newsletter
October 2020
October 2020 Project Update Newsletter